[Case Study] A Documentary on the Ceramic Lining Installation for Large Elbows in an Inner Mongolia Lithium Battery Project

08-29-2026 KINGCERA

Recently, the Kingcera installation team completed a ceramic installation project for large elbows in the Inner Mongolia lithium battery industry. Located at a lithium battery material production line in Inner Mongolia, the project involved installing a set of large-scale segmented elbows (shrimp elbows) for the associated drying equipment. From site entry to final delivery, the entire process lasted nearly half a month, with an installation difficulty significantly higher than that of conventional pipeline construction.
 
Unlike previous projects, this marked the Kingcera installation team’s first off-site installation of large-scale stainless steel equipment. Previous installation targets were mostly equipment in steel and cement plants, which were relatively small and primarily composed of cast iron or ordinary steel structures. In contrast, this project involved large-sized stainless steel elbows; the scale and weight of the equipment were much greater than before, requiring the installation team to readjust their operating habits for lifting, flipping, and welding support. Furthermore, stainless steel is more “delicate” than ordinary steel, as surface scratches and bumps leave obvious marks; thus, extra caution was mandatory during on-site handling and construction, posing a considerable challenge to the installation team.
 
ceramic lined elbow
Large-Diameter Ceramic-Lined Elbow
 
The difficulty in installing segmented elbows lies in the fact that they are not one-piece standard components, but are instead spliced together from multiple pipe sections. Since the developed dimensions of each section vary, it is necessary to loft, mark, and cut them one by one on-site before welding them into a complete elbow curve. After welding, a ceramic lining must be laid on the inner wall; because the interior of the elbow is a curved surface, almost no standard-sized ceramic tile can be used directly, and the vast majority must be re-cut and trimmed according to the actual curvature before being pasted into place piece by piece. This ceramic pasting process alone consumed the majority of the on-site time.
 
Compared with technical challenges, the on-site environment serves as a more direct constraining factor. Located on the Inner Mongolian plateau, the project site featured a dry climate and long sunshine hours, with almost no shelters, leaving the entire working area completely exposed to the sun. During the construction period, the installation team started work at 7:30 AM and finished at 8:00 PM every day, with only an hour and a half for lunch and rest in between. For the remaining ten-plus hours, the workers operated entirely outdoors. Under prolonged exposure to the sun, metal tools became too hot to hold, and crouching next to the pipes caused their backs to burn; however, with a strict deadline and successive procedures, the technicians never once interrupted their work due to the scorching heat.
 
After tile installation is completed, epoxy grout application shall be carried out in accordance with the procedure. The lithium battery industry imposes installation requirements for ceramic lined pipeline inner walls that are far more stringent than those in the traditional steel and cement industries—demanding not only that the ceramic tiles be firmly adhered, but also setting extremely high standards for the flatness of the surface treatment, the uniformity of the gaps, and the neatness and aesthetic appeal of the seams. However, under the intense sunlight in Inner Mongolia, this procedure encountered much greater trouble than anticipated. The adhesiveness of the tape increased significantly under high temperatures and prolonged sun exposure, making it difficult to remove completely without tearing; it frequently broke off deep within the gaps, requiring extra time to clean out one by one. An even more energy-consuming issue was the adhesive residue. Due to the large diameter of the pipeline and the extensive ceramic pasting area, a considerable amount of time had elapsed between the pasting of the last ceramic tile and the client’s approval to proceed with the final seam sealing. The seam sealant quickly dried and solidified in the dry and hot climate; by the time the technicians began cleaning, the adhesive residue on the edges of the tiles had hardened into a thin yet highly tough film adhering to the ceramic surface, rendering ordinary wet cloth wiping completely ineffective and forcing them to soften it before scraping it off inch by inch with a spatula, resulting in labor and time consumption during the seam-cleaning phase that far exceeded conventional projects. Nevertheless, to meet the lithium client’s delivery standards of a smooth, flat, and burr-free finish, the technicians did not cut any corners, repeatedly and thoroughly treating every inch of the seams.
 
Ultimately, all procedures were completed according to the standards. The ceramic tiles on the inner wall of the elbow were neatly arranged, the gaps were cleanly processed, and the seam sealant was fully filled with straight edges, leading to a successful handover following the client’s on-site acceptance.
 
ceramic lined elbow
 
Reflecting on the entire installation process, there were no sudden technical difficulties; the true test for the installation team was their endurance in a protracted battle—facing a lack of prior experience with large stainless steel equipment, an unshaded outdoor environment with high temperatures and intense sunlight, and the lithium industry’s nearly harsh cosmetic requirements for surfaces. Under such multiple pressures, they maintained a stable quality of work for a continuous half-month, executing every routine procedure flawlessly. The welds had to be perfectly tight, the ceramic tiles needed to be individually cut and fitted, the stainless steel surface could not have any scratches, and the adhesive residue had to be thoroughly cleaned—these requirements hold true whether in Changsha or Inner Mongolia, leaving absolutely no room for compromise.
 
Kingcera’s installation team travels across the country year-round, having experienced both the hot and humid rainy seasons of the south and the dry, cold climates of the north. This Inner Mongolia project is simply another successful case of delivering a project according to the exact same standards under varying environmental conditions.

(Original link: 【案例】内蒙古锂电项目大弯头贴瓷安装纪实 )
  Samuel Wu / Translated